14–18
Days sea freight, West Coast
30–35
Days, East Coast via Panama
CARB P2
Formaldehyde baseline
25%
Section 301 on cabinets
16
Weeks door to door
Short answer

Most US multifamily projects buy cabinets from China on FOB terms and handle tariff, clearance and installation locally. The two decisions that move landed cost most are the compliance route and the port. West Coast routing takes 14–18 days; East Coast via Panama takes 30–35, and the difference in inland freight often decides the port.

Key takeaways
  • CARB P2 and TSCA Title VI are the compliance baseline; ask for a report naming your board grade.

  • Section 301 adds 25% on Chinese cabinets; model it before comparing quotes.

  • West Coast is 14–18 days, East Coast 30–35; inland freight often decides the port.

  • ISF must be filed 24 hours before loading; a late filing is the most common cause of holds.

  • A 16-week schedule holds only if shop drawings are approved in week two.

1. What US buyers actually verify

US buyers verify three things before deposit: formaldehyde compliance, structural specification and tariff classification. The first is CARB P2 or TSCA Title VI; the second is board thickness and hardware; the third is the HTS code, because it decides the duty line. A factory that can produce all three in writing has usually shipped to the US before.

Ask for the emission report that matches the panel, not just the factory. A certificate naming the plant but not the board grade proves very little when a customs broker or a lender asks for evidence.

2. Four sourcing routes compared

RouteWhat you buyLead timeBest for
Direct factory FOBCustom cabinets to your spec16 weeksProjects above 30 units
Importer stockStandard sizes from a US warehouse2–4 weeksSmall jobs and fill-ins
Local distributorBranded cabinets, installed6–8 weeksSingle-family and retail
HybridFactory boxes, local fronts12–14 weeksDesign-led multifamily

The route decides who carries tariff, freight and defect risk. Direct FOB is cheapest per unit but puts compliance and clearance on you.

3. Five documents to request before deposit

  • CARB P2 or TSCA Title VI test report naming your board grade

  • Hardware specification with model numbers

  • Shop drawing sample for one typical unit

  • Packaging specification for sea freight

  • Pre-shipment inspection scope and checklist

These five documents are also the ones a customs broker will ask for if an entry is queried. Having them before deposit saves a week later.

4. Where the money goes per unit

Cost lineShare of landed cost
Factory price55–65%
Freight and insurance8–12%
Section 301 tariff15–20%
Clearance and delivery5–8%
Installation10–15%

The tariff line is the one most often left out of the first quote. At 25% on cabinet value it is larger than freight on most routes. Model both in the landed cost guide before comparing.

5. Shipping and clearance into the US

RoutePortTransit
West CoastLos Angeles / Long Beach, Seattle14–18 days
East CoastNew York / New Jersey, Savannah30–35 days
GulfHouston28–32 days

Importer Security Filing must be lodged 24 hours before loading. A late ISF is the most common cause of CBP holds, and the hold costs more than the filing. Check the packaging standard before the container is packed, not after.

6. Installation and defect management

US installation is usually subcontracted, so defect responsibility is split across three parties. Agree before delivery who inspects on arrival, who fixes what, and what counts as a defect rather than site damage. Photograph every damaged carton before opening, because a claim without a photo is a negotiation.

7. Vetting a factory in 12 checks

  1. Business and export licence

  2. CARB P2 / TSCA report

  3. Board supplier invoices

  4. Hardware brand authorisation

  5. Shop drawing capability

  6. Edge banding line

  7. Packing standard

  8. Container loading photos

  9. US shipment references

  10. Inspection history

  11. Lead time record

  12. After-sales response

The checks that matter most are the ones you can verify remotely: the emission report, the hardware authorisation and the loading photos. The rest can wait for a factory visit.

8. A schedule that holds

WeekMilestone
1–2Drawings, approval, deposit
3–9Production and in-line checks
10Pre-shipment inspection
11Loading and ISF filing
12–14Sea freight to US port
15Clearance and site delivery
16Installation and snagging

The schedule fails at week two, not week twelve. If drawings are not approved by the end of week two, every later milestone moves by the same number of days.

9. Common mistakes on a first shipment

Three mistakes show up on almost every first shipment. The first is a certificate that names the factory but not the board grade. The second is a quote that leaves out the Section 301 tariff. The third is a drawing approved after production starts, which moves every later date. Each is cheap to prevent and expensive to fix.

10. What to put in the purchase order

The purchase order should state the board grade, hardware model, door finish, packing standard and inspection scope. It should also name the Incoterm, the port and the party responsible for CARB P2 evidence. A PO that lists only sizes and colours leaves the important terms to interpretation. Attach the hardware specification and the packaging standard as annexes.

11. Lead time and cash

Most factories ask for 30% deposit and the balance before loading. That means cash leaves your account roughly ten weeks before the container arrives. Model the working capital, not just the unit price, and hold back a retention until the pre-shipment inspection is signed off. The landed cost guide shows how to include the financing cost.

12. A worked example

Take a 60-unit apartment kitchen with a cabinet value of about $180,000 FOB. Freight adds 8–12%, the Section 301 tariff adds its share, and installation adds 10–18% of the installed cost. The factory price is roughly two-thirds of the landed total; everything else is the route. Two ports can move the same cabinet by several hundred dollars per unit, which is why the route decision should come before the factory negotiation. Run the numbers in the landed cost guide before asking for a second factory quote.

Planning a US project and comparing routes?
Send us the unit count, port and specification and we will model landed cost with tariff for both coasts.

Frequently asked questions

Is CARB P2 enough for US projects?

For most residential and multifamily work, yes: CARB P2 is the baseline and TSCA Title VI is the federal rule that mirrors it. Ask for a test report that names the board grade you are buying, not just the factory.

How much is the Section 301 tariff?

The current rate on Chinese-origin cabinets is 25% of the declared value. It is charged at import, sits on top of duty, and should be modelled before comparing factory quotes.

Can I avoid the tariff by shipping from another country?

Only if the goods are genuinely produced there and meet rules of origin. Trans-shipping without substantial transformation risks penalties and is not a compliance strategy.

Which coast should I ship to?

West Coast if the project is west of the Rockies: 14–18 days and lower inland freight. East Coast if the project is in the Northeast or Southeast, where 30–35 days at sea still beats cross-country trucking.

Do I need a US importer of record?

Yes. Either you or a licensed customs broker acts as importer of record. The importer carries duty liability and is responsible for ISF filing and record keeping.

How long does clearance take?

Typically two to five days for a clean entry. Holds add a week or more, and most holds trace to a late ISF, a missing certificate or a valuation query.

BFP
BFP Project Team
Cabinetry manufacturing & export · since 2016

This guide is based on live project files: specification reviews, pre-shipment inspection reports and clearance documents from apartment, townhouse and villa work. Where a figure varies by project we give the range rather than a single number. Standards and duty treatment should be confirmed against the current version and your own customs broker.

  Send floor plans and unit count — drawings and per-unit price back within 24 hours.
Get a project proposal
Send your floor plans and unit count — we reply with shop drawings and a per-unit quote.
Reply within 24 hours by email.
Key facts at a glance
MarketUS multifamily, single-family, hospitality
ComplianceCARB P2 / TSCA Title VI
TariffSection 301, 25% on cabinet value
RoutingWest Coast 14–18 days, East Coast 30–35
PortsLA/LB, NY/NJ, Savannah, Houston
Lead time30–45 days production, 16 weeks door to door
Related Project Cases
All projects →
Product categories
All categories →


×

Contact Us

Full Name *
Business Email *
WhatsApp / Phone (Fast Response)
Project Type (Optional)
Estimated Units / Quantity (Optional)
Project Details / Message *

This website utilizes cookies.

We employ cookies to analyze website traffic and enhance your browsing experience. Data securely aggregated, privacy protected. See Privacy Policy for details.

I agree