Short answer

UK projects buy from China on FOB terms and clear through Felixstowe, Southampton or London Gateway in 30–35 days. Post-Brexit the paperwork changed: UKCA marking, a customs declaration and 20% VAT at import. The underlying economics did not. The route still decides whether direct factory supply beats a local distributor.

Key takeaways
  • Sea freight to the UK is 30–35 days; Felixstowe and Southampton take most volume.

  • UKCA marking replaced CE for in-scope products; check scope per component.

  • VAT at import is 20%, usually recoverable but a cash-flow item.

  • Northern Ireland follows a different customs regime; quote it separately.

  • Document errors, not shipping time, cause most customs delays.

1. What UK buyers actually verify

UK buyers verify marking, board grade and fire performance where relevant. UKCA is the marking regime for in-scope products; E1 board is common in residential work; and build-to-rent projects often ask for evidence on both. The factory should be able to name the board supplier and the marking position in writing.

2. Four sourcing routes compared

RouteWhat you buyLead timeBest for
Direct factory FOBCustom cabinets to your spec16 weeksBuild-to-rent above 30 units
UK importer stockStandard sizes from a UK warehouse2–4 weeksSmall jobs and fill-ins
Local distributorBranded cabinets, installed6–8 weeksSingle dwellings and retail
HybridFactory boxes, UK fronts12–14 weeksDesign-led schemes

Brexit added a customs step to every route, but it did not change the ranking. Direct FOB remains cheapest per unit above about 30 units.

3. Five documents to request before deposit

  • Board emission report and board supplier name

  • UKCA or CE position statement for in-scope components

  • Hardware specification with model numbers

  • Shop drawing sample for one typical unit

  • Pre-shipment inspection scope and checklist

The marking statement is the one most often missing. Ask for the position in writing rather than a logo on a brochure.

4. Where the money goes per unit

Cost lineShare of landed cost
Factory price58–68%
Freight and insurance8–12%
Duty0–5%
Clearance and delivery5–8%
Installation12–18%

VAT sits outside this table because it is usually recoverable. Cash flow still matters: 20% on the customs value is paid at import and reclaimed later.

5. Shipping and clearance into the UK

PortBest forTransit
FelixstoweMidlands, East of England30–35 days
SouthamptonSouth coast, South West30–35 days
London GatewayLondon and the South East30–34 days

Send the commercial invoice, packing list and marking statement to the broker before the vessel arrives. Most delays are document mismatches, not inspections. Packaging should meet the export standard before loading.

6. Installation and defect management

UK installation is usually subcontracted per site. Agree the inspection point, the defect definition and the replacement lead time before delivery. For build-to-rent, keep a spares pack per unit type, because matching a door finish six months later is harder than storing one spare door now.

7. Vetting a factory in 12 checks

  1. Business and export licence

  2. Board emission report

  3. UKCA or CE position

  4. Hardware brand authorisation

  5. Shop drawing capability

  6. Edge banding line

  7. Packing standard

  8. Container loading photos

  9. UK shipment references

  10. Inspection history

  11. Lead time record

  12. After-sales response

8. A schedule that holds

WeekMilestone
1–2Drawings, approval, deposit
3–9Production and in-line checks
10Pre-shipment inspection
11Loading and export clearance
12–15Sea freight to UK port
15–16Customs, delivery, installation

The UK leg is longer at sea than the US West Coast, so the approval date matters more. Two weeks lost at drawing stage is two weeks lost on site.

9. Common mistakes on a first shipment

Three mistakes show up on almost every first shipment. The first is a certificate that names the factory but not the board grade. The second is a quote that leaves out VAT and duty at import. The third is a drawing approved after production starts, which moves every later date. Each is cheap to prevent and expensive to fix.

10. What to put in the purchase order

The purchase order should state the board grade, hardware model, door finish, packing standard and inspection scope. It should also name the Incoterm, the port and the party responsible for UKCA marking. A PO that lists only sizes and colours leaves the important terms to interpretation. Attach the hardware specification and the packaging standard as annexes.

11. Lead time and cash

Most factories ask for 30% deposit and the balance before loading. That means cash leaves your account roughly ten weeks before the container arrives. Model the working capital, not just the unit price, and hold back a retention until the pre-shipment inspection is signed off. The landed cost guide shows how to include the financing cost.

12. A worked example

Take a 60-unit apartment kitchen with a cabinet value of about $180,000 FOB. Freight adds 8–12%, VAT and duty at import adds its share, and installation adds 10–18% of the installed cost. The factory price is roughly two-thirds of the landed total; everything else is the route. Two ports can move the same cabinet by several hundred dollars per unit, which is why the route decision should come before the factory negotiation. Run the numbers in the landed cost guide before asking for a second factory quote.

Planning a UK scheme and comparing routes?
Send us the unit count, port and specification and we will model landed cost with VAT and duty.

Frequently asked questions

Is UKCA marking required for cabinets?

UKCA applies to products within the scope of UK product regulations. Cabinets are not always in scope, but hardware and some fitted components may be. Confirm the scope with your importer before assuming a mark is needed.

Does CE marking still work in the UK?

CE is no longer automatically recognised for products that require UKCA. Some categories accept both during transition, but the safe approach is to check the current UK rule for each component.

How much VAT do I pay at import?

Standard VAT is 20% on the customs value plus duty and freight. It is usually recoverable if you are VAT-registered, but it still affects cash flow.

Which UK port should I use?

Felixstowe and Southampton take most container traffic from China. London Gateway is growing and can be faster for London and the Southeast.

How long does customs take post-Brexit?

A clean entry is usually one to three days. Missing or mismatched documents are the main cause of delay, so send the commercial invoice and packing list to the broker before arrival.

Can I ship to Northern Ireland?

Northern Ireland follows different rules under the Windsor Framework. Treat it as a separate customs route and confirm the applicable regime before quoting.

BFP
BFP Project Team
Cabinetry manufacturing & export · since 2016

This guide is based on live project files: specification reviews, pre-shipment inspection reports and clearance documents from apartment, townhouse and villa work. Where a figure varies by project we give the range rather than a single number. Standards and duty treatment should be confirmed against the current version and your own customs broker.

  Send floor plans and unit count — drawings and per-unit price back within 24 hours.
Get a project proposal
Send your floor plans and unit count — we reply with shop drawings and a per-unit quote.
Reply within 24 hours by email.
Key facts at a glance
MarketUK residential, build-to-rent, hospitality
ComplianceUKCA marking, E1 board common
Tax20% VAT at import
Routing30–35 days to Felixstowe or Southampton
PortsFelixstowe, Southampton, London Gateway
Lead time30–45 days production, 16 weeks door to door
Related Project Cases
All projects →
Product categories
All categories →


×

Contact Us

Full Name *
Business Email *
WhatsApp / Phone (Fast Response)
Project Type (Optional)
Estimated Units / Quantity (Optional)
Project Details / Message *

This website utilizes cookies.

We employ cookies to analyze website traffic and enhance your browsing experience. Data securely aggregated, privacy protected. See Privacy Policy for details.

I agree